BREDL and our chapter Concerned Citizens of Shell Bluff file Motion to reopen and submit amended contention regarding Plant Vogtle Unit 3

Dec. 29, 2020: The Nuclear Regulatory Commission Answer claims that BREDL has relied on predecisional material in this matter. This is incorrect. BREDL is relying on material that was contemporaneous with its intervention yet withheld from public scrutiny. This information, which was used by NRC to reach its decision to approve SNC's license amendment request, was provided to BREDL only after a lengthy FOIA response period.

The NRC should have rejected SNC's license amendment request. Our principal interests are significant safety issues, the health and safety of our members living near the plant and the general public. We hearby request that the Commission reopen LAR-20-001.